Using the Project Gantt Chart

A Project's Gantt Chart is a useful visual for Project Management to visualise the steps required to complete the project and where in that sequence of events the project is currently at. Moreover, the tasks that the Gantt chart is comprised of can be edited directly from the visual. For example, the Start Date and Finish Date of each task can be adjusted by simply dragging the length of the item.

Accessing a Project's Gantt Chart

  1. Navigate to Projects > Projects

A screenshot showing how to navigate to the projects table

  1. Open a Project. You can find a specific project by either scrolling through the list or using the search bar.

A screenshot showing how to find the desired project from the projects list

  1. Click on the Project Management tab

A screenshot showing the location of the project management tab for the user to click on

  1. Click on the Gantt tab

A screenshot showing the location of the Gantt tab for the user to click on to display the Gantt Chart

Adjusting the Start and End dates of a Project's Tasks

  1. Navigate to a Project's Gantt Chart by doing the following:
    • Navigate to Projects > Projects.
    • Open a Project item. You can find this project by either scrolling through the list or using the search bar.
    • Click on the Project Management tab
    • Click on the Gantt tab
Detailed Steps

The above steps are discussed in more detail here: Accessing a Project's Gantt Chart

  1. Identify the task where you wish to alter the Start Date or End Date

  2. Click and drag the front of the task to edit the Start Date

A screenshot showing how to edit the start date of the task on the Gantt chart by clicking and dragging the left handle

  1. Click and drag the end of the task to edit the End Date

A screenshot showing how to edit the end date of a task on the Gantt chart by clicking and dragging the right handle

  1. Click and drag the middle of the task to shift the both the Start Date and End Date

A screenshot showing how to change both the start and end dates of a task on a gantt by clicking and dragging the whole task item left or right

  1. Press Save X Items

A screenshot showing the location of the Save button, to save all changes made to tasks on the Gantt

Creating Finish-to-Start Dependencies on a Project's Gantt Chart

A Gantt Chart dependency is a relationship between two or more tasks in a project that dictates the sequence in which they must be executed. Dependencies illustrate the order and timing of task completion, outlining the relationships that exist between different project activities. A Finish-to-Start dependency is the most common type, where the start of one task depends on the completion of another. Task B cannot begin until Task A finishes. Follow the steps below to create Finish-to-Start Dependencies:

  1. Navigate to a Project's Gantt Chart by doing the following:
    • Navigate to Projects > Projects.
    • Open a Project item. You can find this project by either scrolling through the list or using the search bar.
    • Click on the Project Management tab
    • Click on the Gantt tab
Detailed Steps

The above steps are discussed in more detail here: Accessing a Project's Gantt Chart

  1. Identify the task you wish to create a dependency from (Task A) and the task to you wish to create a dependency to (Task B)

  2. Hover your cursor over Task A, you will notice a white circle appear at the end of this task. Click and drag your cursor to the white circle at the start of Task B.

A screenshot showing the user how to connect a task to another in a Gantt chart with a Finish-to-Start Dependency

  1. This results in the Task B start date shifted to the Task A End date. There is logic to accommodate non-work days.

A screenshot showing the result of adding a Finish-to-Start dependency and how the dates of the respective tasks have shifted

  1. Press Save X Items

A screenshot showing the location of the Save button so that users can save the tasks that now have a a Finish-to-Start dependency

Gantt Charts

For further information on using Gantt Charts and creating other dependencies see the full Gantt documentation at: Gantt Basics

Editing a Task from a Project's Gantt Chart

  1. Navigate to a Project's Gantt Chart by doing the following:
    • Navigate to Projects > Projects.
    • Open a Project item. You can find this project by either scrolling through the list or using the search bar.
    • Click on the Project Management tab
    • Click on the Gantt tab
Detailed Steps

The above steps are discussed in more detail here: Accessing a Project's Gantt Chart

  1. Double-click on the task you want to edit

A screenshot showing how the user should double click on Gantt task to open the task item

  1. Edit any relevant fields on the sub item page as needed.

A screenshot showing the details of the sub-item and fields that can be edited

  1. Once you have finished editing, click on Save or Save and Close

A screenshot showing the location of the save button so that users can save any of the edits they made against the task